EGA Al Taweelah Alumina - Refinery Control Room

Client Logo
CLIENT: Emirates Global Aluminium
Date: 2017
Location: Abu Dhabi, UAE

EGA engaged Jackson Lane for concept design of a new control room at their new Al Taweelah Alumina Refinery in Abu Dhabi, UAE. The new control building is part of a major greenfields refinery development which is itself part of an integrated refinery, smelter and downstream manufacturing complex.

Jackson Lane was responsible for all Architectural, and Interior design for the control room and adjacent equipment and training rooms and worked in close cooperation with Honeywell who were responsible for all process control systems design and implementation for the plant as a whole.

The new control room interior was fitted out with 4 operator control stations each with space for 2 operators. We were responsible for the detailed design of custom made operator console desk furniture to be provided under the building contractor’s scope of supply. This included 6 operator console desks with motorised height adjustment, including 2 simulator consoles and 5 operators work desks

The layout incorporated large format video display systems for CCTV and process overviews. This is intended to maximise the information available to all panel operators and shift supervisors in abnormal situations.

Special consideration was given to innovative lighting arrangements and acoustic treatment to provide the most comfortable and ergonomic working conditions for the control room operators.